Documents
Documents Required for Initial Review
Send available documents early so technical issues can be identified before submission.
Project and drawings
- Site location plan
- Architectural / structural / civil drawings
- PUB service plans if available
- Proposed scope of engineering works
- Contractor contact and project schedule
Construction and risk information
- Method statement
- Construction sequence
- Excavation / piling / ERSS details
- Temporary works drawings
- Risk assessment
- Protection measures for sewer or water main
- CCTV report where applicable
- PE / QP endorsement where applicable